Pretty good progress made over the weekend.
Unfortunately not too many pictures.
Got the lower noggings fitted and the DPM trimmed back on Saturday morning.
On Saturday afternoon Ian assisted in getting the 25mm polystyrene fitted to the walls and ceiling.
Here's a pic (taken through garage window so apologies for the reflection)
After that we got some of the plasterboard cut and fitted and got to the point we'd need to turn the power off to fit the boards around the sockets so finished off by removing the window between the garage and the shed.
Sunday saw the plasterboard 90% finished on the walls (I can't fit the last bits until the doors are installed) and the ceiling plasterboard all done.
Tonight's job will be putting the rest of the screws in the plasterboard and start thinking about skrimming and filling the joints.