As Chris seems incapable of asking -
- Can anyone spare a day or so (or even a morning) over the christmas period (
Ideally 27 & 28 - But also 29 & 30 too) to assist with the Duster.
I Believe the plan as it stands is as follows -
Saturday the 24.
The Duster is moved to the Unit (at Leighton Buzzard) to dry out over christmas.
Prep the area. Get dust sheets up etc . . .
Tuesday the 27.
The Front end. The Wings need to be finished being hung - Volunteers !
Also the cowl (I'll do) and Final prep.
Wednesday the 28.
Front end must be finished and prepped.
Doors must be (Very) nearly done too.
Thursday the 29.
Doors finished and prepped.
Roof/Posts Finished and prepped.
Also as much of the rear quarters and boot lid as I can possibly do.
Friday the 30.
Spraying.
(Ideally) Monday 2 Jan.
Transfer to the Barn (Brackley)
There'll be other odds and sods which need doing that will help but obviously the priority is the bodywork.